We work with our Registered Social Landlord (RSL) partners to deliver new housing to meet our priorities, as set out in the Local Housing Strategy.
Using funding from the Scottish Government, our own and RSL partner's resources, we have plans to develop new build housing across the Falkirk Council area. As well as building our own housing, we make nominations to a percentage of RSL new build properties.
Our 5 year plan is set out in the Strategic Housing Investment Plan (SHIP). The SHIP is approved annually by Executive Committee.
It's important to be aware that the planned sites and time scales can change for a number of reasons, such as unexpected costs, planning issues or funding availability.
Latest list of sites to be developed for new affordable housing
Falkirk Council
We plan to build the following:
timescales are subject to change
Site |
Number of properties |
Estimated site start |
Estimated completion |
Woodend Farm |
111 |
August 2022 |
January 2025 |
Haugh Gardens, Bainsford |
40 |
January 2023 |
January 2025 |
Former Denny High (Phase 1) |
137 |
January 2026 |
January 2029 |
Banknock South, Banknock |
106 |
To be confirmed |
To be confirmed |
Seabegs, Bonnybridge |
31 |
To be confirmed |
To be confirmed |
King Street, Stenhousemuir |
21 |
To be confirmed |
To be confirmed |
Larbert Nursery |
14 |
To be confirmed |
To be confirmed |
Haugh Gardens
We (Falkirk Council) plan to build 40 new affordable homes to replace the flats off Haugh Street, Bainsford. The new homes will become part of the Council's housing stock to help meet affordable housing demand in the Falkirk area.
We plan on building a variety of homes from 1 bedroom flats to 4 bedroom houses to provide a broad range of accommodation.
The images below will help you see what the area will look like when it's finished.
Please note these plans will also be subject to receiving all the statutory consents including planning approval.
Leaflet given to local residents:
- Downloads
-
Haugh Gardens leaflet
PDF file, 5 MB
Registered Social Landlords
Our Registered Social Landlord (RSL) partners build Social Rent, Mid-Market Rent (MMR) and Shared Equity properties.
Falkirk Council have agreements in place with each RSL partner that allows for us to nominate a percentage of tenants for new build social rent properties. This helps to provide homes to those on the Council waiting list. However, the percentage differs for each partner and does not include other tenures, like MMR or Shared Equity, therefore if you are interested in any new builds being delivered by our partner RSLs, it is advisable to sign up to their own waiting lists.
Links to our RSL partners webpages and what they plan to build are shown below:
Link Group Ltd
Site |
Number of properties |
Estimated site start |
Estimated completion |
Commissioner Street, Bo'ness |
30 |
May 2023 |
May 2025 |
Rosemead Terrace, California |
39 |
February 2024 |
November 2025 |
For more information on how to apply for housing through Link, please visit Link Housing.
Castle Rock Edinvar (Places for People)
Site |
Number of properties |
Estimated site start |
Estimated completion |
The Drum |
32 |
August 2024 |
July 2026 |
Reddingmuirhead |
23 |
October 2024 |
May 2026 |
Crawfield (Phase 1) |
34 |
May 2024 |
September 2025 |
Crawfield (Phase 2) |
34 |
August 2025 |
January 2027 |
Places for People contact Falkirk Council when they have a vacancy available. Falkirk Council have full nomination rights. See Places for People for information.
Kingdom Housing Association
Kingdom Housing Association plan to build the following:
Site |
Number of properties |
Estimated site start |
Estimated completion |
Rosebank North (Phase 2) |
13 |
To be confirmed |
To be confirmed |
Kilsyth Road, Banknock (Phase 1) |
30 |
To be confirmed |
To be confirmed |
Kilsyth Road, Banknock (Phase 2) |
38 |
To be confirmed |
To be confirmed |
For more information on how to apply for housing through Kingdom, please visit Kingdom Housing Association.
Cairn Housing Association
Site |
Number of Properties |
Estimated Start Date |
Estimated Completion Date |
Adam Grossert Court, Stenhousemuir |
23 |
To be confirmed |
To be confirmed |
For more information on how to apply for housing through Cairn, please visit Cairn Housing Association.
Loretto Housing Association
Site |
Number of properties |
Estimated site start |
Estimated completion |
Carron Road, Bainsford |
79 |
To be confirmed |
To be confirmed |
Gilston, Polmont |
64 |
To be confirmed |
To be confirmed |
Dennyloanhead (phase 1) |
41 |
To be confirmed |
To be confirmed |
Dennyloanhead (phase 2) |
44 |
To be confirmed |
To be confirmed |
For more information on how to apply for housing through Loretto, please visit Loretto Housing Association.
Hanover Housing Association
For more information on how to apply for housing through Hanover, please visit Hanover Scotland.